eClinicalWorks Standard Implementation Timeline

Implementation Process

After the Customer signs the contract with GroupOne Health Source, the Implementation team initiates the Implementation Process. The Implementation Process consists of the following activities:

  1. Introduction phone call by the Project Manager to schedule a Kick-Off call.
  2. Receipt of the eClinicalWorks Welcome Pak.
  3. A Kick-Off Call with the Project Manager.  She will help the Customer make choices with integration features and provide milestone dates as part of the Implementation timeline
  4. Working on Integration Features
  5. Performing Network Check
  6. Performing Installation
  7. Performing Training & Go-Live for Customer and staff
  8. Performing Lab Integration (optional)

At this time the implementation process is completed, and the practice is up and running with eClinicalWorks.

new-ecw-products

Implementation Timeline

The following Implementation Timeline is a guideline, for a typical implementation. Each practice has its own individual requirements; therefore, it is only a suggested standard, not a guarantee.  This does not include time for data migration, lab interface, or Clearinghouse approval.  Typically the Go-Live date is set with your Project Manager once all of your hardware is received and your IT staff has installed your network and hardware.

Note:  Estimated Timeline may be less for Practices that utilize GroupOne's eCW Billing Services.

      Week 1:             

  • Receive signed contract
  • Schedule Kick-Off call & send Welcome Pack
  • Perform Kick-Off call
  • Start enrollment process with Clearinghouse

      Week 2:             

  • Return EDI Questionnaire and Customer Discovery
  • Data Migration process begins and continues through Implementation (optional)
  • Send hardware specifications to GroupOne Health Source for review and approval
  • Return Section III – IT Information & Checklist  (Your provider license(s) will not be given if this document is not sent back to your project manager at GOHS.)

      Weeks 3-6:        

  • Network Check
  • Installation
  • On-line Training & File Build Begins
  • Training and Go-Live (typically during week 4-6 after hardware is received at client's office)

Weeks 10-14:      Optional follow-up trainings